San Angelo Independent School District Board Agenda Report E3 Entegral Solutions Inc. Amendment #1 – Fire Panel Installation 2026-06-15

Fire Panel Installation Contract Amended for E3 Entegral Solutions Inc.

$1,830,000.00 (amendment); cumulative total $23,611,442.00San Angelo IsdE3 ENTEGRAL SOLUTIONS INCJune 15, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The San Angelo ISD Board is recommended to approve Change Order #1 with E3 Entegral Solutions Inc. for fire panel installation at several campuses, adding $1,830,000.00 to the original contract. The change order was developed following an evaluation of district fire alarm needs and funding is from the 2025 Bond plan.

Contract Details

Contract Amount

$1,830,000.00 (amendment); cumulative total $23,611,442.00

Vendor

E3 ENTEGRAL SOLUTIONS INC

Agency

San Angelo Isd, TX

Contract Type

CONSTRUCTION

Document Date

June 15, 2026

Renewal Info

This is the first change order for this project. The amendment does not exceed the 25% threshold for change orders per Texas law. Original contract was $21,781,442.00; new total is $23,611,442.00.