Final RTU Replacement Payment to C. Acitelli Contractors

Final payment $48,619.64; total project cost $973,592.72 (original contract $1,013,300.00)Triton CollegeC. ACITELLI CONTRACTORS INCApril 21, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Triton College approved final completion and a $48,619.64 final payment to C. Acitelli Contractors, Inc. for the Building B RTU replacement project, bringing the total project cost to $973,592.72, under the original $1,013,300 contract. The construction contract, dated September 5, 2024, has now been fully closed out following certification of final completion.

Contract Details

Contract Amount

Final payment $48,619.64; total project cost $973,592.72 (original contract $1,013,300.00)

Vendor

C. ACITELLI CONTRACTORS INC

Agency

Triton College, IL

Contract Type

CONSTRUCTION

Document Date

April 21, 2026

Contract Term

Contract date September 5, 2024; final completion certified March 16, 2026

Renewal Date

2026-03-16

Renewal Info

One-time construction contract; no renewals indicated. Final payment and certificate of completion close out the agreement.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free