CONSTRUCTIONAMENDED

Moltz Construction to complete WRF expansion phase

The City and County of Broomfield selected Moltz Construction as Construction Manager/General Contractor for the Water Recovery Facility Expansion, with an $18 million early work package already approved. A $42.9 million contract amendment to complete Phase 1 construction will be presented to Council on March 10, 2026.

Status
AMENDED
Document date
March 5, 2026
Contract type
CONSTRUCTION
Vendor
Moltz Construction
Agency
Broomfield County · CO

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$18 million (Early Work Package); planned $42.9 million contract amendment
Contract type
CONSTRUCTION
Contract term
Phase 1 early work approved July 22, 2025; late work package amendment to be presented March 10, 2026
Renewal
Initial CMGC contract funded via an $18 million early work package approved July 22, 2025; a $42.9 million amendment is planned to finalize Phase 1 construction scope under 2026 bond funding.
Document type
Minutes
Source document
Broomfield Water Utilities FLOW Committee Minutes March 2026

Related contracts

Other contracts from Moltz Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Broomfield County?

Moltz Construction was awarded this construction contract by Broomfield County, as recorded on March 5, 2026. The contract value is $18 million (Early Work Package); planned $42.9 million contract amendment.

How much is the Moltz Construction contract with Broomfield County worth?

The Moltz Construction contract with Broomfield County is valued at $18 million (Early Work Package); planned $42.9 million contract amendment, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Broomfield Water Utilities FLOW Committee Minutes March 2026 (Minutes), dated March 5, 2026 from Broomfield County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Moltz Construction hold?

Moltz Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Moltz Construction's profile

What is Broomfield County currently buying?

Explore Broomfield County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Broomfield County's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free