CONSTRUCTIONAPPROVED

City of Albany Awards Construction Contract to Jim Boyd Construction (February 2026)

Albany Utility Board approved an emergency contract with Jim Boyd Construction for collapsed sewer line repairs on 2nd Ave. Alley, with project costs estimated at $254,000–$269,000 including bypass pumping. The contract covers trenchless pipe bursting and manhole replacements.

Status
APPROVED
Document date
February 26, 2026
Contract type
CONSTRUCTION
Vendor
Jim Boyd Construction
Agency
City of Albany · GA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$37,985 (initial PO), $233,880 (additional work); total project approx. $254,000 – $269,000 incl. bypass pumping
Contract type
CONSTRUCTION
Contract term
One-time, project-based (expected construction 30–45 days)
Renewal
Project-specific award with incremental authorization; initial PO for discovery and immediate remediation, followed by expanded scope approval. No renewal or extension; one-time emergency work.
Document type
Agenda
Source document
Albany Utility Board Meeting Agenda February 2026

Related contracts

Other contracts from Jim Boyd Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Albany?

Jim Boyd Construction was awarded this construction contract by City of Albany, as recorded on February 26, 2026. The contract value is $37,985 (initial PO), $233,880 (additional work); total project approx. $254,000 – $269,000 incl. bypass pumping.

How much is the Jim Boyd Construction contract with City of Albany worth?

The Jim Boyd Construction contract with City of Albany is valued at $37,985 (initial PO), $233,880 (additional work); total project approx. $254,000 – $269,000 incl. bypass pumping, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Albany Utility Board Meeting Agenda February 2026 (Agenda), dated February 26, 2026 from City of Albany. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Jim Boyd Construction hold?

Jim Boyd Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Jim Boyd Construction's profile

What is City of Albany currently buying?

Explore City of Albany's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Albany's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free