Station 2 inspection change order increased for ECC

Increase of $50,000 (from $85,000 to $135,000 total allowance)Deer Springs Fire Protection DistrictECCNovember 12, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Deer Springs Fire Protection District Board approved an amendment to Change Order #3 with ECC for Station 2 geotechnical and special inspections, increasing the allowance by $50,000 to a total of $135,000. This change reflects ECC’s updated estimate to complete inspection and testing services for the station project.

Contract Details

Contract Amount

Increase of $50,000 (from $85,000 to $135,000 total allowance)

Vendor

ECC

Agency

Deer Springs Fire Protection District, CA

Contract Type

CONSTRUCTION

Document Date

November 12, 2025

Renewal Info

Original Board approval on July 10, 2024 was $85,000 for Geotechnical/Special Inspections Allowance; on July 9, 2025 the Board increased the allowance to a total of $135,000 via Change Order #3 amendment.