Sewer Pump Station Contract Increased by Change Order
Trusted by teams at
Description
The Carneys Point Township Sewerage Authority approved Resolution 2026-26, authorizing Change Order #4 for the Delaware Ave Pump Station PGSA Interconnection project. The amendment increases the construction contract by $28,914.82, bringing the total to $958,117.70.
Contract Details
Contract Amount
Increase of $28,914.82 (new total $958,117.70; original $937,372.70)
Vendor
DELAWARE AVE PUMP STATION PGSA INTERCONNECTION
Agency
Carneys Point SA, NJ
Contract Type
CONSTRUCTION
Document Date
March 17, 2026
Renewal Info
Change Order #4 increases the contract amount to a revised total of $958,117.70; prior reductions were partially restored by this amendment.
More from Carneys Point SA
Carneys Point Township Sewerage Authority Resolution 2026-31
Carney's Point Sewerage Authority 2026 Authority Budget
Carney's Point Sewerage Authority 2026 Authority Budget
Carney's Point Sewerage Authority 2026 Authority Budget
Carneys Point Township Sewerage Authority Resolution 2026-26 Change Order 4
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.