CONSTRUCTIONAMENDED

WWTP No. 2 Change Order Approved with BAR

Acton Municipal Utility District approved Change Order No. 3 with Bar Constructors, Inc. for the Wastewater Treatment Plant No. 2 Improvements Project, increasing the contract by $5,985.69. The amendment also extends substantial completion to June 29, 2026 and final completion to July 26, 2026 to accommodate field-driven design adjustments.

Status
AMENDED
Document date
May 20, 2026
Contract type
CONSTRUCTION
Vendor
Bar Constructors Inc (bar)
Agency
Acton Mud · TX

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$5,985.69 increase
Contract type
CONSTRUCTION
Contract term
Substantial completion June 29, 2026; final completion July 26, 2026
Renewal date
2026-07-26
Renewal
Change Order No. 3 increases the original construction contract amount by $5,985.69 and extends the substantial and final completion dates to June 29, 2026 and July 26, 2026, respectively.
Document type
Minutes
Source document
Acton Municipal Utility District Minutes 2026-05-20

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Acton Mud?

Bar Constructors Inc (bar) was awarded this construction contract by Acton Mud, as recorded on May 20, 2026. The contract value is $5,985.69 increase.

How much is the Bar Constructors Inc (bar) contract with Acton Mud worth?

The Bar Constructors Inc (bar) contract with Acton Mud is valued at $5,985.69 increase, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Acton Municipal Utility District Minutes 2026-05-20 (Minutes), dated May 20, 2026 from Acton Mud. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Bar Constructors Inc (bar) hold?

Bar Constructors Inc (bar) may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Bar Constructors Inc (bar)'s profile

What is Acton Mud currently buying?

Explore Acton Mud's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Acton Mud's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free