CONSTRUCTIONAMENDED

Anderson Construction Awarded Change Order for Airport Road Pumps

Anderson Construction received a change order valued at approximately $1.1 million to add two pumps at the Airport Road Water Pump Station, with the overall project budget increased as part of CIP amendments.

Status
AMENDED
Document date
June 20, 2026
Contract type
CONSTRUCTION
Vendor
Anderson Construction
Agency
Rivanna Water and Sewer Authority · VA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$1,100,000 (approximate) for change order; total revised project budget $10,984,000
Contract type
CONSTRUCTION
Renewal
Executive Director authorized to execute change orders up to $1.32 million total. Project construction completed 2025, change order and additional pumps expected to be installed after lead time of 6-8 months.
Document type
AgendaPacket
Source document
Rivanna Water & Sewer Authority Board of Directors Meeting Agenda Packet 2026-06-23

Related contracts

Other contracts from Anderson Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Rivanna Water and Sewer Authority?

Anderson Construction was awarded this construction contract by Rivanna Water and Sewer Authority, as recorded on June 20, 2026. The contract value is $1,100,000 (approximate) for change order; total revised project budget $10,984,000.

How much is the Anderson Construction contract with Rivanna Water and Sewer Authority worth?

The Anderson Construction contract with Rivanna Water and Sewer Authority is valued at $1,100,000 (approximate) for change order; total revised project budget $10,984,000, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Rivanna Water & Sewer Authority Board of Directors Meeting Agenda Packet 2026-06-23 (AgendaPacket), dated June 20, 2026 from Rivanna Water and Sewer Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Anderson Construction hold?

Anderson Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Anderson Construction's profile

What is Rivanna Water and Sewer Authority currently buying?

Explore Rivanna Water and Sewer Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Rivanna Water and Sewer Authority's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free