CONSTRUCTIONAMENDED

Mission Avenue Improvements Contract Amended for Change Order

The City of Bellevue is requested to approve Change Order No. 1 to Valley Corporation’s Mission Avenue Improvements construction contract, adding $81,295.52 for unforeseen sewer and utility relocation work. The amendment increases the total contract value to $6,823,778.49 and will adjust substantial and final completion dates to accommodate the additional work.

Status
AMENDED
Document date
August 4, 2026
Contract type
CONSTRUCTION
Vendor
Valley Corporation
Agency
City of Bellevue · NE

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$81,295.52 (change order); new total contract price $6,823,778.49
Contract type
CONSTRUCTION
Contract term
Original substantial completion 08/01/2026; ready for final payment 09/04/2026; revised dates TBD pending change order
Renewal
Original contract times set substantial completion for 08/01/2026 and final payment for 09/04/2026. This is Change Order No. 1, increasing the contract amount and extending contract times, with new substantial and final completion dates to be determined based on MUD relocation activities.
Document type
Contract
Source document
City of Bellevue Contract BPW-240109 Mission Avenue Improvements - Change Order No. 1 2026-08-04

Related contracts

Other contracts from Valley Corporation.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Bellevue?

Valley Corporation was awarded this construction contract by City of Bellevue, as recorded on August 4, 2026. The contract value is $81,295.52 (change order); new total contract price $6,823,778.49.

How much is the Valley Corporation contract with City of Bellevue worth?

The Valley Corporation contract with City of Bellevue is valued at $81,295.52 (change order); new total contract price $6,823,778.49, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in City of Bellevue Contract BPW-240109 Mission Avenue Improvements - Change Order No. 1 2026-08-04 (Contract), dated August 4, 2026 from City of Bellevue. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Valley Corporation hold?

Valley Corporation may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Valley Corporation's profile

What is City of Bellevue currently buying?

Explore City of Bellevue's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Bellevue's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free