Change Order #2 for M.E. Collins 14th & Orange Sewer
Trusted by teams at
Description
The Board approved Change Order #2 with M.E. Collins Contracting for the 14th & Orange Sewer Project, increasing the contract by $6,236.85 to reconcile final quantities. This action adjusts the original construction agreement to reflect actual field conditions.
Contract Details
Contract Amount
$6,236.85
Vendor
M.E. COLLINS CONTRACTING
Agency
City of Wahoo, NE
Contract Type
CONSTRUCTION
Document Date
September 17, 2025
Renewal Info
Second change order to the original 14th & Orange Sewer Project contract; updates contract price based on final quantities. No additional time extension is mentioned.