Town Approves $260K Change Order With Cassanella
Trusted by teams at
Description
The Skaneateles Town Board approved a change order not to exceed $260,000 with contractor Cassanella for the Andrews Road water project, addressing increased HDPE pipe costs and bringing the total contract value to approximately $6.1 million. The project retains a 10% contingency of about $740,000.
Contract Details
Contract Amount
Change order not to exceed $260,000; revised total contract approximately $6.1 million
Vendor
CASSANELLA
Agency
Town of Skaneateles, NY
Contract Type
CONSTRUCTION
Document Date
March 30, 2026
Renewal Info
Approved change order increases original construction contract by up to $260,000; total contract now approximately $6.1 million with 10% contingency retained.
More from Town of Skaneateles
GTS Holdings LLC Proposal Description April 2026
Town of Skaneateles Proposal Site Plan Review and Lot Line Relocation 2026-04-03
Town of Skaneateles Board Meeting Agenda March 2026
Town of Skaneateles Town Board Special Meeting Minutes March 30, 2026
Town of Skaneateles Town Board Meeting Agenda March 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.