Fremont School District 79 Construction Manager Bond Agreement Dec 2025

District 79 CM work order for middle school addition

$4,752,227.00Barber County North Unified School District 254PEPPER CONSTRUCTION COMPANYDecember 19, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Fremont School District 79 and Pepper Construction Company executed Project Work Order #011 for the Middle School Cafeteria & STEM Addition and Renovations with a final cost estimate of $4,752,227.00. Work commences May 18, 2026 with substantial completion milestones in August and December 2026 and a construction manager fee of three percent.

Contract Details

Contract Amount

$4,752,227.00

Vendor

PEPPER CONSTRUCTION COMPANY

Agency

Barber County North Unified School District 254, KS

Contract Type

CONSTRUCTION

Document Date

December 19, 2025

Contract Term

Date of Commencement May 18, 2026; Substantial Completion no later than 8/13/26 for entrances, kitchen interior, etc. and 12/30/26 for addition

Renewal Date

2026-12-30

Renewal Info

Work order is issued under a June 1, 2015 Master Agreement (AIA A133-2009) and is subject to modification by change orders for alternates, allowances, or unit prices; no automatic renewal beyond this project is stated.