Mission Bend Municipal Utility District No. 1 Minutes February 2026

Chloramine Conversion Completion Date Extended to December 2026

Mission Bend Mud 1BROWN & GAY ENGINEERS INCFebruary 16, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board approved the engineer’s report from Brown & Gay Engineers, Inc. and granted a contractor-requested extension of the substantial completion date for the chloramine conversion project to December 31, 2026. The engineer also reported that surface water delivery has been delayed until mid-2027.

Contract Details

Vendor

BROWN & GAY ENGINEERS INC

Agency

Mission Bend Mud 1, TX

Contract Type

CONSTRUCTION

Document Date

February 16, 2026

Contract Term

Completion date extended to December 31, 2026 for chloramine conversion project; surface water delivery now delayed until mid-2027

Renewal Date

2026-12-31

Renewal Info

Project completion deadline for the chloramine conversion contract was amended to December 31, 2026, reflecting schedule impacts from delayed surface water delivery.