City of Lake Alfred City Commission Agenda Packet April 20 2026

Odom Proposes $49K Material Cost Change Order

$49,001City of Lake AlfredODOM CONTRACTING LLCApril 20, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Odom Contracting LLC submitted a $49,001 change order proposal to the City of Lake Alfred for material cost increases tied to upsizing water infrastructure on East Haines Boulevard. The additional costs cover larger valves, piping, and thrust blocks without altering the labor component.

Contract Details

Contract Amount

$49,001

Vendor

ODOM CONTRACTING LLC

Agency

City of Lake Alfred, FL

Contract Type

CONSTRUCTION

Document Date

April 20, 2026

Renewal Info

Change order proposal itemizing material components to be added to the existing water line relocation contract.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free