CONSTRUCTIONRECOMMENDED

CCR Roofing Recommended For Daniel Boone Roof Project

District administration recommends awarding CCR Roofing a construction contract for the Daniel Boone Elementary roof section replacement, with a base bid of $536,287.00 plus a 5% contingency for a total hard cost of $563,101.35. Work will begin after completion of phase II mechanical improvements and is expected to finish by October 23, 2026, funded by the 2027 capital budget.

Status
RECOMMENDED
Document date
May 21, 2026
Contract type
CONSTRUCTION
Vendor
Ccr Roofing
Agency
Francis Howell R-III School District · MO

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$536,287.00 base bid plus 5% contingency ($26,814.35), total project hard cost $563,101.35
Contract type
CONSTRUCTION
Contract term
Construction anticipated to begin after August 1, 2026 and conclude on October 23, 2026
Renewal date
2026-10-23
Renewal
Single construction project for roof section replacement with no renewals described; includes a 5% contingency for unforeseen conditions.
Document type
StaffReport
Source document
Board of Education Staff Report Daniel Boone Elementary Roof Section Replacement 2026-05-21

Related contracts

Other contracts from Ccr Roofing.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Francis Howell R-III School District?

Ccr Roofing was awarded this construction contract by Francis Howell R-III School District, as recorded on May 21, 2026. The contract value is $536,287.00 base bid plus 5% contingency ($26,814.35), total project hard cost $563,101.35.

How much is the Ccr Roofing contract with Francis Howell R-III School District worth?

The Ccr Roofing contract with Francis Howell R-III School District is valued at $536,287.00 base bid plus 5% contingency ($26,814.35), total project hard cost $563,101.35, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in Board of Education Staff Report Daniel Boone Elementary Roof Section Replacement 2026-05-21 (StaffReport), dated May 21, 2026 from Francis Howell R-III School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Ccr Roofing hold?

Ccr Roofing may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Ccr Roofing's profile

What is Francis Howell R-III School District currently buying?

Explore Francis Howell R-III School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Francis Howell R-III School District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free