CONSTRUCTIONAMENDED

Sacramento Area Sewer District Agenda September 2025

Harvest Water Pipeline Project Contract Amended for $2.4M Increase

Original Contract: $40,797,472; Additional Change Order Allowance: $2,447,848; Revised Maximum Contract Value: $44,877,220Sacramento CountyRANGER PIPELINES INCSeptember 10, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Sacramento Area Sewer District is amending its contract with Ranger Pipelines, Inc. for the Harvest Water Central-South Pipelines Project. The Board approved an additional $2,447,848 in change order allowance, bringing the revised contract maximum to $44,877,220 to cover extensive roadwork and unexpected construction issues.

Contract Details

Contract Amount

Original Contract: $40,797,472; Additional Change Order Allowance: $2,447,848; Revised Maximum Contract Value: $44,877,220

Vendor

RANGER PIPELINES INC

Agency

Sacramento County, CA

Contract Type

CONSTRUCTION

Document Date

September 10, 2025

Contract Term

Construction began July 2024; Ongoing, duration not specified

Renewal Date

2026-12-31

Renewal Info

Original contract approved Jan 10, 2024. Allowance for change orders increased Sep 10, 2025; contract total now $44,877,220. Change orders reflect project scope evolution.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free