Change order for Colby Drive stormwater project
Trusted by teams at
Description
St. Peters staff recommends approval of Change Order No. 4 with Kuesel Excavating Co. for the Colby Drive Stormwater Improvement Project, adding $157,729.85 and extending the completion date to August 31, 2026. The amendments address field condition changes, added fencing, and utility-related pipe reconfigurations.
Contract Details
Contract Amount
$157,729.85 (increase); new total $5,396,121.31
Vendor
KUESEL EXCAVATING COMPANY
Agency
City of St. Peters, MO
Contract Type
CONSTRUCTION
Document Date
May 28, 2026
Contract Term
Extended 62 calendar days to August 31, 2026
Renewal Date
2026-08-31
Renewal Info
Change Order No. 4 extends the construction completion deadline by 62 calendar days to August 31, 2026 and raises the cumulative contract value to $5,396,121.31.
More from KUESEL EXCAVATING COMPANY
More from City of St. Peters
City of St. Peters AgendaPacket Board of Aldermen Regular Meeting 2026-05-28
City of St. Peters AgendaPacket Board of Aldermen Regular Meeting 2026-05-28
City of St. Peters AgendaPacket Board of Aldermen Regular Meeting 2026-05-28
City of St. Peters AgendaPacket Board of Aldermen Regular Meeting 2026-05-28
City of St. Peters AgendaPacket Board of Aldermen Work Session Meeting 2026-05-28
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.