City of St. Peters AgendaPacket Board of Aldermen Work Session Meeting 2026-05-28

Change order for Colby Drive stormwater project

$157,729.85 (increase); new total $5,396,121.31City of St. PetersKUESEL EXCAVATING COMPANYMay 28, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

St. Peters staff recommends approval of Change Order No. 4 with Kuesel Excavating Co. for the Colby Drive Stormwater Improvement Project, adding $157,729.85 and extending the completion date to August 31, 2026. The amendments address field condition changes, added fencing, and utility-related pipe reconfigurations.

Contract Details

Contract Amount

$157,729.85 (increase); new total $5,396,121.31

Vendor

KUESEL EXCAVATING COMPANY

Agency

City of St. Peters, MO

Contract Type

CONSTRUCTION

Document Date

May 28, 2026

Contract Term

Extended 62 calendar days to August 31, 2026

Renewal Date

2026-08-31

Renewal Info

Change Order No. 4 extends the construction completion deadline by 62 calendar days to August 31, 2026 and raises the cumulative contract value to $5,396,121.31.