Brighton Central School District 2023 Capital Improvement Project Phase 2 Report January 2026

General trades boiler room work by Steve General

Brighton Central School DistrictSTEVE GENERAL CONTRACTORSJanuary 30, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Brighton Central School District continues its Phase 2 Capital Improvement Project with Steve General Contractors performing general trades work in the high school boiler room under Contract 201. January 2026 activities focused on demolition of the cooling tower steel structure and storage room doors as part of broader mechanical upgrades.

Contract Details

Vendor

STEVE GENERAL CONTRACTORS

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

January 30, 2026

Contract Term

Brighton 2023 Phase 2 Capital Improvement Project, approximately December 1, 2025 – August 31, 2027

Renewal Date

2027-08-31

Renewal Info

Part of the multi-year 2023 Phase 2 Capital Improvement Project general trades contract (Contract 201). No explicit renewal or extension terms stated in the report.

More from STEVE GENERAL CONTRACTORS

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free