Yonkers contract expanded for WTC pump station rehab

Approximately $11.7 million (increase to Contract WTC-354.201)Port Authority of New York and New JerseyYONKERS CONTRACTING CO INCApril 22, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Port Authority reauthorized the Phase IV rehabilitation of the World Trade Center River Water Pump Station, raising the total project cost to $61.8 million and increasing Yonkers Contracting Co. Inc.'s contract by about $11.7 million. The added funds cover unforeseen structural slab replacements and extend construction by roughly 18 months.

Contract Details

Contract Amount

Approximately $11.7 million (increase to Contract WTC-354.201)

Vendor

YONKERS CONTRACTING CO INC

Agency

Port Authority of New York and New Jersey, NJ

Contract Type

CONSTRUCTION

Document Date

April 22, 2026

Contract Term

Construction schedule extended by approximately 18 months

Renewal Info

Amendment to Contract WTC-354.201 adding approximately $11.7 million and extending the construction schedule by about 18 months to complete additional slab repairs.