$951K Change Order Approved for MEB General Contractors
Trusted by teams at
Description
HRSD approved a $951,091 change order with MEB General Contractors, Inc. for Solids System Improvements at Army Base Treatment Plant, increasing the contract value to $5,413,022 and extending the completion to February 2026.
Contract Details
Contract Amount
$951,091 (change order)
Vendor
MEB GENERAL CONTRACTORS INC
Agency
Hampton Roads Sanitation District, VA
Contract Type
CONSTRUCTION
Document Date
August 26, 2025
Contract Term
Additional 302 calendar days
Renewal Date
2026-02-28
Renewal Info
Amendment increases contract by $951,091 to new total $5,413,022; adds 302 days to project schedule; previous change orders totaled $188,931.
More from MEB GENERAL CONTRACTORS INC
Issuing Agency
Special District
Virginia Beach, VA
More from Hampton Roads Sanitation District
HRSD Commission Meeting Minutes 2026-05-26
HRSD Commission Meeting Minutes 2026-05-26
HRSD Commission Meeting Minutes 2026-05-26
HRSD Commission Meeting Minutes 2026-05-26
HRSD Commission Meeting Minutes 2026-05-26
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.