High Point Urban Area MPO Technical Coordinating Committee Agenda April 2026

Pine Street Rail Crossing Closure Progressing with RR Coordination

$4,911,720Housing Authority of the city of High PointSMITH-ROWE LLCApril 20, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Smith-Rowe, LLC is midway through a $4.9 million NCDOT project to close the Pine Street rail crossing and complete associated utility work, with off-railroad tasks largely finished. Further progress depends on finalizing a force account agreement with Norfolk Southern.

Contract Details

Contract Amount

$4,911,720

Vendor

SMITH-ROWE LLC

Agency

Housing Authority of the city of High Point, NC

Contract Type

CONSTRUCTION

Document Date

April 20, 2026

Contract Term

September 7, 2024 – August 30, 2026

Renewal Date

2026-08-30

Renewal Info

No renewal stated; current contract term runs through August 30, 2026.

More from SMITH-ROWE LLC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free