Irondequoit Fire District Board of Fire Commissioners Meeting Minutes April 2026

Engine 172 Build with Pierce Manufacturing Adjusted

approximately $100,000 removed from initial project cost to dateIrondequoit Fire DistrictPIERCE MANUFACTURINGApril 6, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

District officials met with Pierce Manufacturing to adjust the Engine 172 apparatus build, extending the design finalization to late 2026 with delivery expected in August or September 2027 and approximately $100,000 already trimmed from the original cost. Further specification and cost optimization work is continuing.

Contract Details

Contract Amount

approximately $100,000 removed from initial project cost to date

Vendor

PIERCE MANUFACTURING

Agency

Irondequoit Fire District, NY

Contract Type

EQUIPMENT

Document Date

April 6, 2026

Contract Term

Design changes finalized by end of 2026; anticipated delivery August/September 2027

Renewal Date

2027-09-30

More from PIERCE MANUFACTURING

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free