Groundwater Project Contract Scope and Budget Increased

Increase of $2,800,000 for a revised cost limit of $9,926,625San Francisco Public Utilities CommissionJMB CONSTRUCTION INCJune 23, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The SFPUC will amend Contract WD-2878B with JMB Construction, Inc., adding $2,800,000 in contingency for a new limit of $9,926,625 and extending the duration to 1,260 days. The change addresses PG&E grid access delays and adds ammonia treatment facilities at the South Spruce Avenue Well site.

Contract Details

Contract Amount

Increase of $2,800,000 for a revised cost limit of $9,926,625

Vendor

JMB CONSTRUCTION INC

Agency

San Francisco Public Utilities Commission, CA

Contract Type

CONSTRUCTION

Document Date

June 23, 2026

Contract Term

Revised duration limit of 1,260 consecutive calendar days (approximately three years and five months)

Renewal Info

Cost contingency increased by $2,800,000 and duration contingency extended by 270 days, resulting in a total limit of $9,926,625 and 1,260 days.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free