Jersey Heights Stormwater Project Design Approved for $439K
Trusted by teams at
Description
The Morristown Selectboard approved Tyler Mumley as the project engineer for the Jersey Heights 3-acre rural stormwater infiltration chamber plan, with an estimated total project cost of $439,900. The design phase milestones are set for 2025 and construction is scheduled for summer 2026, largely financed through an ARPA grant.
Contract Details
Contract Amount
$439,900 (total estimated cost; $369,000 preliminary construction bid)
Vendor
MUMLEY TYLER
Agency
Morrisville village, VT
Contract Type
PROFESSIONAL_SERVICES
Document Date
March 26, 2025
Contract Term
Design completion deadlines: 60% by May 1, 2025; Landowner buy-in by June 1, 2025; 100% design by September 1, 2025; Construction scheduled early summer 2026
Renewal Date
2026-09-01
Renewal Info
Initial design phase approval; subsequent construction contract to be bid separately. Milestone deadlines for design and landowner engagement outlined; no renewals described.
More from MUMLEY TYLER
More from Morrisville village
Morristown Board of Liquor & Tobacco Control Meeting Minutes May 2026
Morristown Board of Liquor & Tobacco Control Meeting Minutes May 2026
Morristown Board of Liquor & Tobacco Control Meeting Minutes May 2026
Town of Morristown Board of Liquor & Tobacco Control Meeting Agenda May 4, 2026
Town of Morristown Board of Liquor & Tobacco Control Meeting Agenda May 4, 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.