Morristown Selectboard Minutes March 2025

Jersey Heights Stormwater Project Design Approved for $439K

$439,900 (total estimated cost; $369,000 preliminary construction bid)Morrisville villageMUMLEY TYLERMarch 26, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Morristown Selectboard approved Tyler Mumley as the project engineer for the Jersey Heights 3-acre rural stormwater infiltration chamber plan, with an estimated total project cost of $439,900. The design phase milestones are set for 2025 and construction is scheduled for summer 2026, largely financed through an ARPA grant.

Contract Details

Contract Amount

$439,900 (total estimated cost; $369,000 preliminary construction bid)

Vendor

MUMLEY TYLER

Agency

Morrisville village, VT

Contract Type

PROFESSIONAL_SERVICES

Document Date

March 26, 2025

Contract Term

Design completion deadlines: 60% by May 1, 2025; Landowner buy-in by June 1, 2025; 100% design by September 1, 2025; Construction scheduled early summer 2026

Renewal Date

2026-09-01

Renewal Info

Initial design phase approval; subsequent construction contract to be bid separately. Milestone deadlines for design and landowner engagement outlined; no renewals described.