Change Order Boosts Water Main Contract With Pyramid
Trusted by teams at
Description
Needles is poised to approve Change Order 3 with Pyramid Building and Engineering, Inc. for the Water Main and Manifold Improvements Project, adding $196,278.46 and bringing the contract total to approximately $1.5 million. The change order will authorize additional work required to complete the utility improvements.
Contract Details
Contract Amount
$196,278.46 change order; new total contract amount $1,498,98.88 (likely $1,498,978.88)
Vendor
PYRAMID BUILDING AND ENGINEERING INC
Agency
City of Needles, CA
Contract Type
CONSTRUCTION
Document Date
May 12, 2026
Renewal Info
Third change order to the existing Public Works Agreement increases the contract value; the project continues under the amended total until completion.
More from PYRAMID BUILDING AND ENGINEERING INC
More from City of Needles
City of Needles AgendaPacket 2026-06-23
City of Needles Agenda Regular Meeting 2026-06-23
City of Needles Agenda Regular Meeting 2026-06-23
City of Needles Agenda Regular Meeting 2026-06-23
City of Needles Board of Public Utilities Agenda 2026-06-02
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.