City of Needles Agenda Packet 2026-05-12

Change Order Boosts Water Main Contract With Pyramid

$196,278.46 change order; new total contract amount $1,498,98.88 (likely $1,498,978.88)City of NeedlesPYRAMID BUILDING AND ENGINEERING INCMay 12, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Needles is poised to approve Change Order 3 with Pyramid Building and Engineering, Inc. for the Water Main and Manifold Improvements Project, adding $196,278.46 and bringing the contract total to approximately $1.5 million. The change order will authorize additional work required to complete the utility improvements.

Contract Details

Contract Amount

$196,278.46 change order; new total contract amount $1,498,98.88 (likely $1,498,978.88)

Vendor

PYRAMID BUILDING AND ENGINEERING INC

Agency

City of Needles, CA

Contract Type

CONSTRUCTION

Document Date

May 12, 2026

Renewal Info

Third change order to the existing Public Works Agreement increases the contract value; the project continues under the amended total until completion.

More from PYRAMID BUILDING AND ENGINEERING INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free