Hays CISD Jackson Construction Update March 2026

Tri-C advances footing and grade beam work at Kyle Elementary

Hays CisdTRI-CMarch 27, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Tri-C is documented as continuing excavation, rebar work, and concrete footing pours for the Kyle Elementary project, including twelve footings placed on March 27, 2026. The contractor will proceed with further footing and grade beam work in the coming week.

Contract Details

Vendor

TRI-C

Agency

Hays Cisd, TX

Contract Type

CONSTRUCTION

Document Date

March 27, 2026

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free