Norwalk-La Mirada Unified School District Agenda Board of Education Meeting 2026-06-22

Change Order Extends Ramona Windows & Flooring Contract

$21,797.37 (change order increase)Norwalk-La Mirada Unified1ST CALIFORNIA CONSTRUCTIONJune 22, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board will approve Change Order No. 1 with 1st California Construction for the Ramona Windows & Flooring Replacement Project, adding $21,797.37 and extending completion to October 9, 2026. The change addresses extended window manufacturing lead times and several unforeseen site conditions.

Contract Details

Contract Amount

$21,797.37 (change order increase)

Vendor

1ST CALIFORNIA CONSTRUCTION

Agency

Norwalk-La Mirada Unified, CA

Contract Type

CONSTRUCTION

Document Date

June 22, 2026

Contract Term

Contract completion date extended 78 calendar days to October 9, 2026

Renewal Date

2026-10-09

Renewal Info

Change Order No. 1 increases contract sum and extends substantial completion date by 78 days.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free