A-1 Excavating Nears Closeout On Hillcrest Project
Trusted by teams at
Description
The Village of Park Ridge is processing an estimated $165,000 payment to A-1 Excavating for the Hillcrest and Greenbriar project, with $29,000 retained and $31,500 in liquidated damages for delays. Project closeout and release of retainage are expected by the end of May 2026 in preparation for LRIP reimbursement.
Contract Details
Contract Amount
Next payment estimated at approximately $165,000 with $29,000 retainage and $31,500 liquidated damages
Vendor
A-1 EXCAVATING
Agency
Park Ridge village, WI
Contract Type
CONSTRUCTION
Document Date
April 20, 2026
Contract Term
Project closeout anticipated before end of May 2026
Renewal Date
2026-05-31
Renewal Info
Contract is in closeout phase with retainage and liquidated damages applied; no renewals indicated.
More from A-1 EXCAVATING
More from Park Ridge village
Village of Park Ridge Board Meeting Minutes April 20, 2026
Village of Park Ridge Board Meeting Minutes April 20, 2026
Village of Park Ridge Board Meeting Minutes April 20, 2026
Village of Park Ridge Board Meeting Minutes April 20, 2026
Village of Park Ridge Special Board Meeting Minutes April 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.