Bouten Design-Build Contract Nears Substantial Completion
Trusted by teams at
Description
Bouten Construction Company continues work as design-builder for the Pasco Aquatics Facility under a GMP-based progressive design-build contract. The March 2026 schedule update maintains a substantial completion date of May 8, 2026 and final completion on May 22, 2026.
Contract Details
Vendor
BOUTEN CONSTRUCTION COMPANY
Agency
City of Pasco, WA
Contract Type
CONSTRUCTION
Document Date
April 28, 2026
Contract Term
Through May 22, 2026 (final completion); substantial completion May 8, 2026
Renewal Date
2026-05-22
Renewal Info
Project master budget lists a revised construction (PDB) allocation of $39,760,000 within a total project budget of $51,046,928, including contingencies and betterments.
More from BOUTEN CONSTRUCTION COMPANY
More from City of Pasco
Pasco Public Facilities District Board AgendaPacket 2026-06-16
Pasco Public Facilities District Board AgendaPacket 2026-06-16
Pasco Public Facilities District Board AgendaPacket 2026-06-16
Pasco Public Facilities District Board AgendaPacket 2026-06-16
Pasco Public Facilities District Board AgendaPacket 2026-06-16
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.