Pasco Public Facilities District Board Special Meeting Agenda April 2026

Bouten Design-Build Contract Nears Substantial Completion

City of PascoBOUTEN CONSTRUCTION COMPANYApril 28, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Bouten Construction Company continues work as design-builder for the Pasco Aquatics Facility under a GMP-based progressive design-build contract. The March 2026 schedule update maintains a substantial completion date of May 8, 2026 and final completion on May 22, 2026.

Contract Details

Vendor

BOUTEN CONSTRUCTION COMPANY

Agency

City of Pasco, WA

Contract Type

CONSTRUCTION

Document Date

April 28, 2026

Contract Term

Through May 22, 2026 (final completion); substantial completion May 8, 2026

Renewal Date

2026-05-22

Renewal Info

Project master budget lists a revised construction (PDB) allocation of $39,760,000 within a total project budget of $51,046,928, including contingencies and betterments.