Downey Contracting Contract Amended for Cameron Park Project
Trusted by teams at
Description
The subcommittee recommended approval of Change Order No. 2 with Downey Contracting, LLC for C.B. Cameron Park, with an increase of $240,844.60 and adjustment of contract completion to January 27, 2027. Scope includes utility and fixture upgrades.
Contract Details
Contract Amount
$240,844.60 (Change Order No. 2); revised contract total $24,221,955.00
Vendor
DOWNEY CONTRACTING LLC
Agency
Oklahoma City Airport Trust, OK
Contract Type
CONSTRUCTION
Document Date
June 2, 2026
Contract Term
Original completion: (not stated); new completion date: January 27, 2027 (plus 35 days for this change order)
Renewal Date
2027-01-27
Renewal Info
Second change order; contract now increased by 1.05% over original; completion extended by 35 days with this amendment.
More from DOWNEY CONTRACTING LLC
More from Oklahoma City Airport Trust
The City of Oklahoma City Prequalification Review Board Agenda Packet 2026-06-10
The City of Oklahoma City Prequalification Review Board Agenda Packet 2026-06-10
The City of Oklahoma City Prequalification Review Board Agenda Packet 2026-06-10
The City of Oklahoma City Prequalification Review Board Agenda Packet 2026-06-10
The City of Oklahoma City Prequalification Review Board Agenda Packet 2026-06-10
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.