City of Callaway Board of Commissioners Meeting Agenda Packet May 2026

Lift Station Rehab Contract Amended for Added Work

$79,943 (Change Order #1); Total Change Order Cost $74,942.63; Original contract $2,174,001.55; New total $2,248,944.18City of CallawayMAINLINE CONSTRUCTION LLCMay 12, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City of Callaway is considering Change Order #1 with Mainline Construction, LLC for the CDBG-DR Lift Station Rehab Project, adding approximately $79,943 and extending the schedule by 50 days. The amendment covers floodplain elevation changes, additional structural repairs, and ARV drain redesign at several lift stations.

Contract Details

Contract Amount

$79,943 (Change Order #1); Total Change Order Cost $74,942.63; Original contract $2,174,001.55; New total $2,248,944.18

Vendor

MAINLINE CONSTRUCTION LLC

Agency

City of Callaway, MN

Contract Type

CONSTRUCTION

Document Date

May 12, 2026

Contract Term

Additional 50 days requested for completion

Renewal Info

Change Order #1 increases construction compensation by approximately $79,943 and extends the contract by 50 days for coordination and completion of added work across multiple lift stations.