Board Agenda Item April 2026

Cedar Hill ISD Amends CORE Construction Cost Clause

Cedar Hill IsdCORE CONSTRUCTIONApril 18, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Cedar Hill ISD plans to amend its July 29, 2024 construction contract with CORE Construction for the 2024 Bond Program to revise the Cost of the Work provision so that the 4.75% contractor fee is applied once per change order rather than on each individual change. The amendment, documented as AIA G701-2017 Change Order No. 003, does not affect the overall contract sum or project timeline.

Contract Details

Vendor

CORE CONSTRUCTION

Agency

Cedar Hill Isd, TX

Contract Type

CONSTRUCTION

Document Date

April 18, 2026

Contract Term

July 29, 2024 – duration of 2024 Bond Program construction agreement (unchanged)

Renewal Info

Amendment (AIA G701-2017 Change Order No. 003) revises Section 6.1.2 so the 4.75% fee applies a single time to changes in the Cost of the Work instead of to each individual change; no change to contract sum or schedule.