District Extends Gym Alterations Contract Schedule

Taft Union High School District approved Prime Contract Change Order No. 01 with Black Hall Construction for the Mullen Gymnasium General Alterations project, extending the construction period by seven days without changing price or scope. The revised construction start date is February 23, 2026, with completion still scheduled for July 31, 2026.

Status
AMENDED
Document date
February 17, 2026
Contract type
CONSTRUCTION
Vendor
Black Hall Construction
Agency
Taft Union High · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract type
CONSTRUCTION
Contract term
Construction period increased by 7 calendar days; revised construction start date February 23, 2026; construction completion remains July 31, 2026
Renewal date
2026-07-31
Renewal
Change Order No. 01 extends the contract duration from 152 to 159 calendar days with no modification to contract price or scope. Construction start date is adjusted to February 23, 2026 while maintaining the July 31, 2026 completion date.
Document type
Contract
Source document
Taft Union High School District Contract Prime Contract Change Order No. 01 2026-02-17

Related contracts

Other contracts from Black Hall Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Taft Union High?

Black Hall Construction was awarded this construction contract by Taft Union High, as recorded on February 17, 2026.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Taft Union High School District Contract Prime Contract Change Order No. 01 2026-02-17 (Contract), dated February 17, 2026 from Taft Union High. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Black Hall Construction hold?

Black Hall Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Black Hall Construction's profile

What is Taft Union High currently buying?

Explore Taft Union High's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Taft Union High's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free