Change Order adds US 80 waterline crossing
Trusted by teams at
Description
In late 2025 KSA proposed Change Order No. 1 for the HWY 80 Utility Relocation Project totaling $278,229.44 to add a new waterline crossing under US 80 using existing contractor J&L Construction. The change order bundled $14,000 in additional engineering services and $264,229.44 in construction work under the Town’s existing agreements.
Contract Details
Contract Amount
$278,229.44 (change order total, including $14,000 engineering and $264,229.44 construction)
Vendor
KSA
Agency
Town of Sunnyvale, TX
Contract Type
CONSTRUCTION
Document Date
May 11, 2026
Contract Term
Time to complete change order construction: 2 months
Renewal Info
This original version of Change Order No. 1 was later revised by the Town to remove engineering services and update construction pricing, resulting in a revised amount of $276,282.94 focused solely on construction.
More from KSA
More from Town of Sunnyvale
Town of Sunnyvale Town Council Agenda 2026-05-16
Town of Sunnyvale Town Council Agenda 2026-05-16
Town of Sunnyvale Town Council Meeting Agenda May 11, 2026
Town of Sunnyvale Town Council Meeting Agenda May 11, 2026
Town of Sunnyvale Town Council Meeting Agenda May 11, 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.