Fort Dodge City Council AgendaPacket 2026-05-18

Water main project contract amended for Gehrke Inc.

Change Order #1 reducing contract by $75,755.00; Sub-Final Pay Estimate #6 $82,147.78Fort Dodge Airport AuthorityGEHRKE INCMay 18, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Fort Dodge City Council approved Change Order #1 with Gehrke Inc. reducing the Fort Dodge to Manson water main connection contract by $75,755 and authorized Sub-Final Pay Estimate #6 for $82,147.78, along with substantial completion. The amendment adjusts the final construction cost as the project nears closeout.

Contract Details

Contract Amount

Change Order #1 reducing contract by $75,755.00; Sub-Final Pay Estimate #6 $82,147.78

Vendor

GEHRKE INC

Agency

Fort Dodge Airport Authority, IA

Contract Type

CONSTRUCTION

Document Date

May 18, 2026

Renewal Info

Contract amended via Change Order #1 with a $75,755 reduction; project is at substantial completion and moving toward final acceptance.