City of Evanston Administration & Public Works Committee Agenda April 27 2026

Change Order Extends Alley and Sidewalk Project

$225,166.00City of EvanstonALLIANCE CONTRACTORS INCApril 27, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Evanston will amend its 2025 Alley and Sidewalk Improvements contract with Alliance Contractors, Inc., adding $225,166.00 and extending completion to June 26, 2026. The additional funding will come from the Howard and Ridge TIF.

Contract Details

Contract Amount

$225,166.00

Vendor

ALLIANCE CONTRACTORS INC

Agency

City of Evanston, IL

Contract Type

CONSTRUCTION

Document Date

April 27, 2026

Contract Term

Contract completion extended by 217 calendar days to June 26, 2026

Renewal Date

2026-06-26

Renewal Info

Change Order No. 3 extends the existing construction contract by 217 days, setting a new completion date of 2026-06-26 and increasing the total contract value by $225,166.00.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free