Metropolitan Water District of Salt Lake & Sandy Board of Trustees Meeting Minutes May 2025

Salt Lake City to Reimburse Cottonwoods Connection Change Order

$393,832.97 (WCD AB06), credit of $142,718.06 (WCD AB05)Salt Lake-Sandy Metropolitan Water DistrictSALT LAKE CITYMay 19, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board approved Change Order No. AB04 for the Cottonwoods Connection project, with Salt Lake City reimbursing all Work Change Directive costs related to pipeline modifications and an emergency waterline conflict, resulting in a $393,832.97 charge and a $142,718.06 credit.

Contract Details

Contract Amount

$393,832.97 (WCD AB06), credit of $142,718.06 (WCD AB05)

Vendor

SALT LAKE CITY

Agency

Salt Lake-Sandy Metropolitan Water District, UT

Contract Type

CONSTRUCTION

Document Date

May 19, 2025

Renewal Info

Includes change orders and credits; full reimbursement from Salt Lake City, no extension of term specified.