Sound Transit StaffReport Contract Modification for Jacobs Engineering Group for the West Seattle Link Extension project 2026-06-25

Sound Transit Approves Phase 2 Design Contract Option

$238,740,159, with a 20 percent contingency of $47,748,032, totaling $286,488,191, for a total authorized amount not to exceed $341,359,256Central Puget Sound Regional Transit AuthorityJACOBS ENGINEERING GROUP INCJune 25, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Sound Transit Board approved Motion M2026-22 to modify its contract with Jacobs Engineering Group, Inc. to exercise the Phase 2 option for Civil Engineering Design Services on the West Seattle Link Extension. The modification authorizes up to $238.7 million plus contingency, for a total not to exceed $341.4 million over an approximately 22‑month term, contingent on budget amendments under Resolution R2026-14.

Contract Details

Contract Amount

$238,740,159, with a 20 percent contingency of $47,748,032, totaling $286,488,191, for a total authorized amount not to exceed $341,359,256

Vendor

JACOBS ENGINEERING GROUP INC

Agency

Central Puget Sound Regional Transit Authority, WA

Contract Type

PROFESSIONAL_SERVICES

Document Date

June 25, 2026

Contract Term

Approximately 22 months for Phase 2 services, anticipated to start July 1, 2026

Renewal Date

2028-04-30

Renewal Info

Phase 2 is an exercised option (Contract Option 1) under the existing multi-phase Civil Engineering Design Services contract; future Phase 3 bid support and construction administration remain optional and will require separate Board approval to exercise.

More from JACOBS ENGINEERING GROUP INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free