Bellamy Creek generator project change order approved
Trusted by teams at
Description
Wilcox & Dyer, LLC received a $280,484.51 change order for the Bellamy Creek Correctional Facility generator separation project, bringing the total contract to $1,221,820.52. The amendment funds additional electrical work, including a new primary feed and switchgear, to increase capacity.
Contract Details
Contract Amount
Increase $280,484.51
Vendor
WILCOX & DYER LLC
Agency
Michigan Department of Technology, Management and Budget|Administrative Board, MI
Contract Type
CONSTRUCTION
Document Date
June 16, 2026
Renewal Info
Multiple prior change orders approved between 2017 and 2024; Change Order No. 7 increases scope and total contract to $1,221,820.52.
More from WILCOX & DYER LLC
Issuing Agency
State
Lansing, MI
More from Michigan Department of Technology, Management and Budget|Administrative Board
Michigan State Administrative Board Minutes 2026-06-16
Michigan State Administrative Board Minutes 2026-06-16
Michigan State Administrative Board Minutes 2026-06-16
Michigan State Administrative Board Minutes 2026-06-16
Michigan State Administrative Board Minutes 2026-06-16
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.