Electric resiliency construction work order with Garney
Trusted by teams at
Description
The Peace River Manasota Regional Water Supply Authority is asked to approve a work order with Garney Companies, Inc. for plant electric service resiliency improvements, in an amount not to exceed $557,568. The project will repower ASR wells and sludge facilities from existing 480VAC switchgear and replace aging overhead power lines with underground cabling over an approximately 10-week schedule.
Contract Details
Contract Amount
Not-to-exceed $557,568
Vendor
GARNEY COMPANIES INC
Agency
Peace River-Manasota Regional Water Supply Authority, FL
Contract Type
CONSTRUCTION
Document Date
May 23, 2026
Contract Term
Approximately 10-week construction schedule after notice to proceed
Renewal Info
Work order issued under an existing Continuing Services Agreement dated December 1, 2021; this action draws on that agreement but does not modify its overall term.
More from GARNEY COMPANIES INC
Issuing Agency
Special District
Lakewood Ranch, FL
More from Peace River-Manasota Regional Water Supply Authority
Peace River Manasota Regional Water Supply Authority Routine Status Report Peace River Regional Reservoir No. 3 Project 2026-06-05
Peace River Manasota Regional Water Supply Authority Agenda Minutes of April 1, 2026 Board of Directors Meeting 2026-06-05
Peace River Manasota Regional Water Supply Authority Agenda Minutes of April 1, 2026 Board of Directors Meeting 2026-06-05
Peace River Manasota Regional Water Supply Authority StaffReport Plant 2 Concrete Restoration 2026-06-05
Peace River Manasota Regional Water Supply Authority StaffReport Regional Integrated Loop System Phase 2B Interconnect Project 2026-06-05
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.