Final Payment and Change Order Approved for Peltier
Trusted by teams at
Description
Fort Bend County MUD No. 169 approved final payment of $342,386.27 to Peltier Brothers Construction, LLC for the Cross Creek Ranch Effluent Redistribution project and authorized a $125,375.34 contract decrease via Change Order No. 2. The Board accepted the project as complete following the engineer's recommendation.
Contract Details
Contract Amount
$342,386.27; Change Order No. 2 decrease of $125,375.34
Vendor
PELTIER BROTHERS CONSTRUCTION LLC
Agency
Fort Bend County Mud 169, TX
Contract Type
CONSTRUCTION
Document Date
March 2, 2026
Renewal Info
Change Order No. 2 decreases the original construction contract amount by $125,375.34 and serves as the final adjustment with project acceptance.
More from PELTIER BROTHERS CONSTRUCTION LLC
More from Fort Bend County Mud 169
Fort Bend County MUD 169 Board Meeting Minutes March 2026
Fort Bend County MUD 169 Board Meeting Minutes March 2026
Fort Bend County Municipal Utility District No. 169 Minutes March 2026
Fort Bend County Municipal Utility District No. 169 Minutes March 2026
Fort Bend County MUD No. 169 Meeting Agenda March 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.