Marble Falls City Council awarded Trimbuilt Construction, Inc. a contract not to exceed $5,732,798.24 for construction of Fire Station No. 2 and offsite improvements. The project aims to enhance emergency response and lower community insurance costs. The work is to be completed within roughly 13 months from Notice to Proceed.
Contract Details
Contract Amount
Not to exceed $5,732,798.24
Vendor
TRIMBUILT CONSTRUCTION INC
Agency
City of Marble Falls, TX
Contract Type
CONSTRUCTION
Document Date
February 17, 2026
Contract Term
375 calendar days for substantial completion; 400 calendar days for final payment after Notice to Proceed (NTP)
Renewal Date
2027-03-12
Renewal Info
No explicit renewal; change orders can amend cost or term. Project duration based on NTP plus 375/400 calendar days.
More from TRIMBUILT CONSTRUCTION INC
More from City of Marble Falls
City of Marble Falls Council Meeting Minutes April 21 2026
City of Marble Falls Council Meeting Agenda March 2026
City of Marble Falls Council Meeting Agenda March 2026
City of Marble Falls Council Meeting Agenda March 2026
City of Marble Falls Council Meeting Agenda March 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.