Ventura awarded the State Water Interconnection Pipeline construction contract to Sam Hill & Sons as the lowest responsive and responsible bidder, with a term of 1,098 days from Notice to Proceed and contingency authority bringing the total not-to-exceed amount to $44,714,179. The Council also set oversight requirements for use of construction contingency.

Status
AWARDED
Document date
July 14, 2026
Contract type
CONSTRUCTION
Vendor
Sam Hill & Sons
Agency
City of San Buenaventura (Ventura) · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Base construction bid amount not specified plus contingency up to $5,833,000 for a total not to exceed $44,714,179
Contract type
CONSTRUCTION
Contract term
1,098 consecutive calendar days from Notice to Proceed, plus potential 165-day extension
Renewal
Initial construction contract for WA08-1052 with 1,098-day duration and up to 165 days of additional time and $5,833,000 in contingency, for a total not-to-exceed $44,714,179.
Document type
Minutes
Source document
City of Ventura Minutes Action Agenda 2026-07-14

Related contracts

Other contracts from Sam Hill & Sons.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of San Buenaventura (Ventura)?

Sam Hill & Sons was awarded this construction contract by City of San Buenaventura (Ventura), as recorded on July 14, 2026. The contract value is Base construction bid amount not specified plus contingency up to $5,833,000 for a total not to exceed $44,714,179.

How much is the Sam Hill & Sons contract with City of San Buenaventura (Ventura) worth?

The Sam Hill & Sons contract with City of San Buenaventura (Ventura) is valued at Base construction bid amount not specified plus contingency up to $5,833,000 for a total not to exceed $44,714,179, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record, structured as a not-to-exceed (ceiling) agreement.

Where was this contract approved?

This contract appears in City of Ventura Minutes Action Agenda 2026-07-14 (Minutes), dated July 14, 2026 from City of San Buenaventura (Ventura). Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Sam Hill & Sons hold?

Sam Hill & Sons may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Sam Hill & Sons's profile

What is City of San Buenaventura (Ventura) currently buying?

Explore City of San Buenaventura (Ventura)'s vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of San Buenaventura (Ventura)'s profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free