CONSTRUCTIONRECOMMENDED

Change Order Expands CMP Replacement Contract

City staff propose a change order to Contract No. 2026-016 with Infrastructure Solutions, LLC, adding $117,967.50 for CMP replacement at Monticello East and near Mill Valley High School. The amendment would raise the total contract amount to $1,287,934.50.

Status
RECOMMENDED
Document date
August 7, 2026
Contract type
CONSTRUCTION
Vendor
Infrastructure Solutions Llc
Agency
Town of Shawnee · KS

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$117,967.50 increase (new total $1,287,934.50)
Contract type
CONSTRUCTION
Renewal
Change order to existing Contract No. 2026-016 increasing scope and total contract value to $1,287,934.50.
Document type
Agenda
Source document
City of Shawnee City Council Agenda 2026-08-10

Related contracts

Other contracts from Infrastructure Solutions Llc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Town of Shawnee?

Infrastructure Solutions Llc was awarded this construction contract by Town of Shawnee, as recorded on August 7, 2026. The contract value is $117,967.50 increase (new total $1,287,934.50).

How much is the Infrastructure Solutions Llc contract with Town of Shawnee worth?

The Infrastructure Solutions Llc contract with Town of Shawnee is valued at $117,967.50 increase (new total $1,287,934.50), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in City of Shawnee City Council Agenda 2026-08-10 (Agenda), dated August 7, 2026 from Town of Shawnee. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Infrastructure Solutions Llc hold?

Infrastructure Solutions Llc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Infrastructure Solutions Llc's profile

What is Town of Shawnee currently buying?

Explore Town of Shawnee's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Town of Shawnee's profile