Change order extends and increases valve replacement contract
Trusted by teams at
Description
The Brick Township Municipal Utilities Authority approved Change Order No. 1 with Pillari Brothers Construction Corp. for the Water Treatment Plant and Distribution System Valve Replacement Project. The order adds $10,706.50 to the contract and extends the final completion date by 147 days to March 20, 2026.
Contract Details
Contract Amount
Increase of $10,706.50 (new total $240,332.50; original $229,626.00)
Vendor
PILLARI BROTHERS CONSTRUCTION CORP
Agency
Brick Township MUA, NJ
Contract Type
CONSTRUCTION
Document Date
November 25, 2025
Contract Term
147 calendar day no cost time extension; final completion date revised from October 24, 2025 to March 20, 2026
Renewal Date
2026-03-20
Renewal Info
Change Order No. 1 amends Capital Contract No. 725015X by adding $10,706.50 and extending the final completion date by 147 calendar days to March 20, 2026.
More from PILLARI BROTHERS CONSTRUCTION CORP
More from Brick Township MUA
Brick Township Municipal Utilities Authority Public Meeting Agenda April 2026
Brick Township Municipal Utilities Authority Public Meeting Agenda April 2026
Brick Township Municipal Utilities Authority Public Meeting Agenda April 2026
Brick Township Municipal Utilities Authority Public Meeting Agenda April 2026
Brick Township Municipal Utilities Authority Public Meeting Agenda April 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.