brick_township_municipal_utilities_authority_resol.pdf

Change order extends and increases valve replacement contract

Increase of $10,706.50 (new total $240,332.50; original $229,626.00)Brick Township MUAPILLARI BROTHERS CONSTRUCTION CORPNovember 25, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Brick Township Municipal Utilities Authority approved Change Order No. 1 with Pillari Brothers Construction Corp. for the Water Treatment Plant and Distribution System Valve Replacement Project. The order adds $10,706.50 to the contract and extends the final completion date by 147 days to March 20, 2026.

Contract Details

Contract Amount

Increase of $10,706.50 (new total $240,332.50; original $229,626.00)

Vendor

PILLARI BROTHERS CONSTRUCTION CORP

Agency

Brick Township MUA, NJ

Contract Type

CONSTRUCTION

Document Date

November 25, 2025

Contract Term

147 calendar day no cost time extension; final completion date revised from October 24, 2025 to March 20, 2026

Renewal Date

2026-03-20

Renewal Info

Change Order No. 1 amends Capital Contract No. 725015X by adding $10,706.50 and extending the final completion date by 147 calendar days to March 20, 2026.

More from PILLARI BROTHERS CONSTRUCTION CORP

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free