CONSTRUCTIONAMENDED

lake-delton-village-change-order-for-east-durkee-street-extension_f7b.pdf

Lake Delton extends and increases Durkee Street contract

$20,653.50 (increase); new total $195,920.00 (was $175,266.50)Lake Delton villageALLEN STEELE COMPANY INCOctober 2, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Village of Lake Delton approved a change order with Allen Steele Co., Inc. for the East Durkee Street Extension - Phase 1 project, adding $20,653.50 for additional select borrow material. The amendment brings the total contract value to $195,920.00 and extends substantial completion to October 10, 2025.

Contract Details

Contract Amount

$20,653.50 (increase); new total $195,920.00 (was $175,266.50)

Vendor

ALLEN STEELE COMPANY INC

Agency

Lake Delton village, WI

Contract Type

CONSTRUCTION

Document Date

October 2, 2025

Contract Term

Substantial completion extended from 10/1/2025 to 10/10/2025; final payment date remains 11/1/2025

Renewal Date

2025-11-01

Renewal Info

This is Change Order No. 1 modifying the original construction contract by increasing the price and extending the substantial completion date by 9 days; final payment date remains unchanged at 11/1/2025.