Duchesne City Council Meeting Minutes March 10 2026

City Increases Master Plan Contract With Horrocks Engineering

Increase master plan budget to $175,000 (original budget $100,000; current cost approx. $156,000; remaining estimate $10,000–$15,000)City of DuchesneHORROCKS ENGINEERINGMarch 10, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Duchesne City Council amended its master plan contract with Horrocks Engineering, setting a new maximum project cost of $175,000 to complete citywide utility and infrastructure planning. The increase responds to expanded scope requirements and remaining work on QA/QC, mapping, and final report preparation.

Contract Details

Contract Amount

Increase master plan budget to $175,000 (original budget $100,000; current cost approx. $156,000; remaining estimate $10,000–$15,000)

Vendor

HORROCKS ENGINEERING

Agency

City of Duchesne, UT

Contract Type

PROFESSIONAL_SERVICES

Document Date

March 10, 2026

Renewal Info

Original budget of $100,000 (to match a $50,000 CIB grant) was informally understood to be insufficient for a full master plan; Council action formally raises the cap to $175,000 and establishes it as the maximum project cost.