CONSTRUCTIONAMENDED

San Francisco Public Utilities Commission Resolution Log 2026-05-27

San Joaquin Pipeline Contract Duration Extended

No change to contract amountSan Francisco Public Utilities CommissionMOUNTAIN CASCADE INCMay 27, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The SFPUC extended the duration contingency for Contract HH-1009 with Mountain Cascade Inc. to 765 days to complete San Joaquin Pipeline valve and safe entry improvements, with no change to contract cost.

Contract Details

Contract Amount

No change to contract amount

Vendor

MOUNTAIN CASCADE INC

Agency

San Francisco Public Utilities Commission, CA

Contract Type

CONSTRUCTION

Document Date

May 27, 2026

Contract Term

Revised duration limit of 765 calendar days (approximately two years and one month)

Renewal Info

Duration contingency increased by 208 days; no cost change.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free