CONSTRUCTIONAMENDED

Hoover New Campus contract expanded with Change Order 4

Palo Alto Unified School District approved Change Order No. 4 with XL Construction for the Hoover New Campus, adding $283,489.74 in building and site modifications. The expanded scope covers mechanical and electrical soffits, plumbing and casework changes, storm drainage upgrades, and additional fencing, leaving $237,235.78 in remaining contingency.

Status
AMENDED
Document date
November 1, 2025
Contract type
CONSTRUCTION
Vendor
Xl Construction
Agency
Palo Alto Unified · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Change Order No. 4: $283,489.74; Previously Approved: $2,446,084.48; Cumulative Change Orders Total: $2,729,574.22
Contract type
CONSTRUCTION
Renewal
Major construction contract modified via Change Order No. 4 with multiple additive and one deductive PCOs; cumulative change orders now total $2,729,574.22 against the project contingency.
Document type
Report
Source document
Palo Alto Unified School District Change Order Report 2025-11-01

Related contracts

Other contracts from Xl Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Palo Alto Unified?

Xl Construction was awarded this construction contract by Palo Alto Unified, as recorded on November 1, 2025. The contract value is Change Order No. 4: $283,489.74; Previously Approved: $2,446,084.48; Cumulative Change Orders Total: $2,729,574.22.

How much is the Xl Construction contract with Palo Alto Unified worth?

The Xl Construction contract with Palo Alto Unified is valued at Change Order No. 4: $283,489.74; Previously Approved: $2,446,084.48; Cumulative Change Orders Total: $2,729,574.22, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Palo Alto Unified School District Change Order Report 2025-11-01 (Report), dated November 1, 2025 from Palo Alto Unified. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Xl Construction hold?

Xl Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Xl Construction's profile

What is Palo Alto Unified currently buying?

Explore Palo Alto Unified's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Palo Alto Unified's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free