Michigan State Administrative Board Meeting Minutes April 2026

Christman Fish Hatchery Infrastructure Contract Expanded

Increase $2,791,240.00 (Total Contract $10,500,000.00)Michigan Department of Technology, Management and Budget|Administrative BoardTHE CHRISTMAN COMPANYApril 14, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Christman Company received a $2,791,240 change order for Southern Infrastructure Projects at multiple state fish hatcheries, raising the contract total to $10.5 million. The added funds support construction packages for a new cool water fish rearing facility at Wolf Lake State Fish Hatchery.

Contract Details

Contract Amount

Increase $2,791,240.00 (Total Contract $10,500,000.00)

Vendor

THE CHRISTMAN COMPANY

Agency

Michigan Department of Technology, Management and Budget|Administrative Board, MI

Contract Type

CONSTRUCTION

Document Date

April 14, 2026

Renewal Info

Tenth change order with multiple prior amendments approved in 2024–2026.